Sundon Substation πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / eastern /
Dates
First heard 2022-01-26
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Pivot Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.931115+-0.498819
Coordinates
51.931115, -0.498819
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
497 / 9315

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Sundon Substation / eastern
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2022-10
Planning Permission Expired: -> 26/01/2025

2022-04
Record Last Updated (dd/mm/yyyy): 16/07/2021 -> 30/03/2022
Site Name: Sundon Substation - 49.9MW Battery Storage -> Sundon Substation
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 26/01/2022