Maiden, Annfield Plain - Energy Storage ππ
Status
planning
Country / State / Closest City
π¬π§ uk / north east /
Dates
First heard |
2021-08-18 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
38
π This is an estimate
Maximum Power in MW
38
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Stephenson Mohl Development /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.848812+-1.732319
Coordinates
54.848812, -1.732319
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
482 / 9036
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Maiden, Annfield Plain - Energy Storage / north east
Go live / estimated go live
/
MW
38
Status
planning
Changes:
2022-10
Record Last Updated (dd/mm/yyyy): 13/12/2021 -> 28/07/2022
Planning Permission Expired: -> 18/08/2026
2021-12
Record Last Updated (dd/mm/yyyy): 18/05/2021 -> 13/12/2021
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 18/08/2021