Dersalloch Battery Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2021-11-29
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Scottish Power Renewables (UK) Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.321678+-4.477597
Coordinates
55.321678, -4.477597
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
475 / 8927

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Dersalloch Battery Storage Facility / scotland
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2022-10
Planning Permission Expired: -> 29/11/2026

2021-12
Record Last Updated (dd/mm/yyyy): 28/04/2021 -> 22/12/2021
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 29/11/2021