National Grids Rainhill Substation Battery storage facility ππ
Status
planning
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2021-03-02 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
57
π This is an estimate
Maximum Power in MW
57
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Sizing John Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.419678+-2.738489
Coordinates
53.419678, -2.738489
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
466 / 8439
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
National Grids Rainhill Substation Battery storage facility / north west
Go live / estimated go live
/
MW
57
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 21/10/2022 -> 02/08/2021
2023-01
Record Last Updated (dd/mm/yyyy): 02/03/2021 -> 21/10/2022
Development Status: Planning Permission Granted -> Revised
Development Status (short): Awaiting Construction -> Revised
Are they re-applying (New REPD Ref): -> 11559
2022-10
Planning Permission Expired: -> 07/06/2024
2022-04
Address: οΏ½Land To The South Of National Grid's Rainhill Substation Lea Green Road Sutton Manor St Helens WA9 4QH -> οΏ½Land To The South Of National Grid's Rainhill Substation Lea Green Road Sutton Manor St Helens