Minchens Lane Battery Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south east /
Dates
First heard 2021-10-08
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Penso Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.331436+-1.066893
Coordinates
51.331436, -1.066893
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
465 / 8434

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Minchens Lane Battery Storage Facility / south east
Go live / estimated go live
/
MW
100
Status
planning
Changes:
2024-04
Planning Authority: Basingstoke & Deane Borough Council -> Basingstoke and Deane Borough Council
Planning Permission Refused: 08/10/2021 ->

2024-01
Record Last Updated (dd/mm/yyyy): 03/02/2023 -> 21/09/2023
Appeal Lodged: -> 22/12/2021

2023-07
Record Last Updated (dd/mm/yyyy): 02/03/2021 -> 03/02/2023
Development Status: Planning Application Submitted -> Appeal Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Authority: Basingstoke and Deane Borough Council -> Basingstoke & Deane Borough Council
Planning Permission Refused: -> 08/10/2021
Appeal Granted: -> 26/01/2023
Planning Permission Granted: -> 26/01/2023
Planning Permission Expired: -> 26/01/2026