Cottom Power Station πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / east midlands /
Dates
First heard 2021-01-12
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ EDF Energy Thermal Generation Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.303393+-0.781494
Coordinates
53.303393, -0.781494
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
459 / 8278

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Cottom Power Station / east midlands
Go live / estimated go live
/
MW
50
Status
planning
Changes: