Newlands Farm Battery Storage Facility Phase 2 πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south east /
Dates
First heard 2021-01-12
Construction start 2022-02-27
Operation start 2022-09-01
Estimated start
Construction time 7 months -> 5 MWh/m
Capacity in MWh
40
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ British Solar Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:50.83301+-1.191431
Coordinates
50.83301, -1.191431
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
455 / 8264

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Newlands Farm Battery Storage Facility Phase 2 / south east
Go live / estimated go live
2022-09-01 /
MW
40
Status
operation
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 18/03/2022 -> 15/02/2024
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Planning Permission Expired: 26/01/2024 -> 45317
Under Construction: -> 27/02/2022
Operational: -> 01/09/2022
status: planning -> operation 🍾 πŸŽ‰ 🍸

2024-01
Record Last Updated (dd/mm/yyyy): 12/01/2021 -> 18/03/2022

2022-10
Planning Permission Expired: -> 26/01/2024

2021-12
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Permission Granted: -> 26/01/2021