Platchaig House, Kilmorack - Battery Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2021-08-02
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Whirlwind Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:57.469701+-4.507613
Coordinates
57.469701, -4.507613
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
453 / 8248

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Platchaig House, Kilmorack - Battery Storage Facility / scotland
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 02/08/2021 -> 31/07/2023
Development Status: Planning Application Submitted -> Revised
Development Status (short): Application Submitted -> Revised
Are they re-applying (New REPD Ref): -> 14373
Planning Permission Refused: -> 30/08/2022