Lower Dunton Road Battery Storage Facility πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / eastern /
Dates
First heard 2021-02-24
Construction start 2024-02-19
Operation start
Estimated start
Construction time
Capacity in MWh
28
πŸ“ This is an estimate
Maximum Power in MW
28
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Eku Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.56649+0.39129
Coordinates
51.56649, 0.39129
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
451 / 8213

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Lower Dunton Road Battery Storage Facility / eastern
Go live / estimated go live
/
MW
28
Status
construction
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 11/01/2022 -> 22/02/2024
Operator (or Applicant): Cedar Tech Developments Limited -> Eku Energy
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Under Construction: -> 19/02/2024
status: planning -> construction πŸ—οΈ

2024-01
Record Last Updated (dd/mm/yyyy): 24/02/2021 -> 11/01/2022

2022-10
Planning Permission Expired: -> 05/02/2024