Coventry National Grid Substation πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / west midlands /
Dates
First heard 2021-01-22
Construction start 2022-07-01
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Pivot Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.454379+-1.464323
Coordinates
52.454379, -1.464323
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
423 / 7885

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Coventry National Grid Substation / west midlands
Go live / estimated go live
/
MW
49
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 11/11/2022 -> 25/06/2020

2023-01
Record Last Updated (dd/mm/yyyy): 07/02/2021 -> 11/11/2022
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Under Construction: -> 01/07/2022
status: planning -> construction πŸ—οΈ