Clauchrie Windfarm Battery ππ
Status
cancelled
Country / State / Closest City
π¬π§ uk / scotland /
Dates
First heard |
2020-03-31 |
Construction start |
|
Operation start |
|
Estimated start |
|
Month disappeared |
2024-01 |
Construction time |
|
Capacity in MWh
25
π This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Scottish Power Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.163369+-4.677241
Coordinates
55.163369, -4.677241
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
417 / 7804
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2023-07
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Clauchrie Windfarm Battery / scotland
Go live / estimated go live
/
MW
25
Status
cancelled
Changes:
2023-07
Record Last Updated (dd/mm/yyyy): 31/03/2020 ->
2024-01
This project disappeared in the
2024-01
report.
That's why the status was set to
cancelled