Lister Drive ππ
Status
operation
Country / State / Closest City
π¬π§ uk / north west /
Dates
First heard |
2021-05-07 |
Construction start |
2021-05-01 |
Operation start |
2022-08-01 |
Estimated start |
|
Construction time |
15 months -> 3 MWh/m
|
Capacity in MWh
49
π This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arenko Cleantech / Stratcraft /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.419914+-2.927592
Coordinates
53.419914, -2.927592
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
408 / 7740
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Lister Drive / north west
Go live / estimated go live
2022-08-01 /
MW
49
Status
operation
Changes:
2024-04
Under Construction: 01/05/2021 ->
2024-01
Record Last Updated (dd/mm/yyyy): -> 04/01/2023
Operator (or Applicant): Arenko Cleantech -> Arenko Cleantech / Stratcraft
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Operational: -> 01/08/2022
status: construction -> operation πΎ π πΈ
2023-07
Record Last Updated (dd/mm/yyyy): 17/05/2022 ->
2022-07
Record Last Updated (dd/mm/yyyy): 07/05/2021 -> 17/05/2022
2022-04
Address: Land Adjacent to Lister Drive, Carnegie Road, Liverpool, Merseyside -> Land Adjacent to Lister Drive, Carnegie Road, Liverpool,