Feeder Road πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2021-05-21
Construction start 2023-01-01
Operation start 2024-01-09
Estimated start
Construction time 12 months -> 1 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Thrive Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.447495+-2.565063
Coordinates
51.447495, -2.565063
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
405 / 7663

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Feeder Road / south west
Go live / estimated go live
2024-01-09 /
MW
20
Status
operation
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 01/05/2023 -> 22/01/2024
Development Status: Finished -> Operational
Development Status (short): Finished -> Operational
Operational: -> 09/01/2024

2024-01
Record Last Updated (dd/mm/yyyy): 13/06/2023 -> 01/05/2023

2023-07
Record Last Updated (dd/mm/yyyy): 20/05/2022 -> 13/06/2023
Development Status: Planning Permission Granted -> Finished
Development Status (short): Awaiting Construction -> Finished
Under Construction: -> 01/01/2023
status: planning -> operation 🍾 πŸŽ‰ 🍸

2022-07
Record Last Updated (dd/mm/yyyy): 21/05/2021 -> 20/05/2022