Energy Centre Royal Mint πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / wales /
Dates
First heard 2019-12-09
Construction start 2022-05-01
Operation start 2023-08-01
Estimated start
Construction time 15 months -> 1 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Infinite Energy Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.555048+-3.390758
Coordinates
51.555048, -3.390758
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
403 / 7684

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Energy Centre Royal Mint / wales
Go live / estimated go live
2023-08-01 /
MW
20
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 16/02/2022 -> 01/08/2023
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Under Construction: -> 01/05/2022
Operational: -> 01/08/2023
status: planning -> operation 🍾 πŸŽ‰ 🍸

2022-04
Record Last Updated (dd/mm/yyyy): 17/08/2020 -> 16/02/2022
Development Status: Under Construction -> Planning Permission Granted
Development Status (short): Under Construction -> Awaiting Construction
Under Construction: 01/04/2021 ->
status: construction -> planning