Lisnabreeny Road πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / northern ireland /
Dates
First heard 2019-06-21
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
36
πŸ“ This is an estimate
Maximum Power in MW
36
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Energia Group /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.555765+-5.864088
Coordinates
54.555765, -5.864088
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
392 / 7556

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Lisnabreeny Road / northern ireland
Go live / estimated go live
/
MW
36
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 25/06/2020

2023-07
Record Last Updated (dd/mm/yyyy): 25/06/2020 ->