Harestanes Windfarm ππ
Status
planning
Country / State / Closest City
π¬π§ uk / scotland /
Dates
First heard |
2019-12-20 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ ScottishPower Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.264014+-3.560109
Coordinates
55.264014, -3.560109
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
380 / 7395
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Harestanes Windfarm / scotland
Go live / estimated go live
/
MW
100
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 25/06/2020
2023-07
Record Last Updated (dd/mm/yyyy): 25/06/2020 ->