Pillswood Phase 2 ππ
Status
operation
Country / State / Closest City
uk / yorkshire and humber /
Dates
First heard |
2019-11-14 |
Construction start |
2022-04-01 |
Operation start |
2022-11-01 |
Estimated start |
|
Construction time |
7 months -> 7 MWh/m
|
Capacity in MWh
49
π This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Harmony Energy Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.802281+-0.416949
Coordinates
53.802281, -0.416949
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
376 / 7360
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2023-07
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Pillswood Phase 2 / yorkshire and humber
Go live / estimated go live
2022-11-01 /
MW
49
Status
operation
Changes:
2023-07
Record Last Updated (dd/mm/yyyy): 09/11/2022 ->
2023-01
Record Last Updated (dd/mm/yyyy): 31/01/2020 -> 09/11/2022
Operator (or Applicant): Northern Powergrid -> Harmony Energy Storage
Site Name: Creyke Beck Substation -> Pillswood Phase 2
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Are they re-applying (Old REPD Ref) : 7005 ->
Under Construction: -> 01/04/2022
Operational: -> 01/11/2022
status: planning -> operation πΎ π πΈ
2022-10
Are they re-applying (Old REPD Ref) : -> 7005