Minety South - Battery Storage πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2017-07-19
Construction start
Operation start 2022-10-01
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Statera Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.601469+-1.98817
Coordinates
51.601469, -1.98817
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
362 / 7184

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Minety South - Battery Storage / south west
Go live / estimated go live
2022-10-01 /
MW
49
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 21/08/2020

2023-07
Record Last Updated (dd/mm/yyyy): 21/08/2020 ->

2023-01
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Operational: -> 01/10/2022
status: planning -> operation 🍾 πŸŽ‰ 🍸

2022-10
Site Name: Minety South Battery Storage -> Minety South - Battery Storage
Installed Capacity (MWelec): 50 -> 49.99
mw: 50 -> 49