Whitelee Wind Farm Battery Storage Extension πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2019-06-10
Construction start 2020-10-01
Operation start 2021-10-01
Estimated start
Construction time 12 months -> 4 MWh/m
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Scottish Power Renewables (formerly Arcus Consultancy Services) /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.695517+-4.171399
Coordinates
55.695517, -4.171399
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
359 / 7174

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Whitelee Wind Farm Battery Storage Extension / scotland
Go live / estimated go live
2021-10-01 /
MW
50
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 21/02/2022

2023-07
Record Last Updated (dd/mm/yyyy): 21/02/2022 ->

2022-04
Record Last Updated (dd/mm/yyyy): 29/04/2020 -> 21/02/2022
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Under Construction: -> 01/10/2020
Operational: -> 01/10/2021
status: planning -> operation 🍾 πŸŽ‰ 🍸