Osbaldwick Substation πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / yorkshire and humber /
Dates
First heard 2019-11-14
Construction start 2022-05-01
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ UK Battery Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.957798+-1.019392
Coordinates
53.957798, -1.019392
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
358 / 7172

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Osbaldwick Substation / yorkshire and humber
Go live / estimated go live
/
MW
49
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/07/2022

2023-07
Record Last Updated (dd/mm/yyyy): 27/07/2022 ->

2022-10
Record Last Updated (dd/mm/yyyy): 14/11/2019 -> 27/07/2022
Development Status: Planning Permission Granted -> Under Construction
Development Status (short): Awaiting Construction -> Under Construction
Address: Os Field 5070, Hull Road, Dunnington, York, North Yorkshire -> Os Field 5070, Hull Road, Dunnington, York,
Planning Application Reference: 18/02659/OUT -> 20/01515/REM
Planning Application Submitted: 21/11/2018 -> 21/08/2020
Planning Permission Granted: 22/02/2019 -> 08/10/2020
Planning Permission Expired: 22/02/2022 ->
Under Construction: -> 01/05/2022
status: planning -> construction πŸ—οΈ