Braintree Road Substation πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / eastern /
Dates
First heard 2019-01-16
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Pivot Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.864838+0.578226
Coordinates
51.864838, 0.578226
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
356 / 7161

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Braintree Road Substation / eastern
Go live / estimated go live
/
MW
49
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 06/09/2022

2023-07
Record Last Updated (dd/mm/yyyy): 06/09/2022 ->

2022-10
Record Last Updated (dd/mm/yyyy): 17/09/2020 -> 06/09/2022
Development Status: Planning Permission Granted -> Revised
Development Status (short): Awaiting Construction -> Revised
Are they re-applying (New REPD Ref): -> 11995