Fideoak Mills πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2020-02-21
Construction start 2019-09-01
Operation start 2020-08-01
Estimated start
Construction time 11 months -> 2 MWh/m
Capacity in MWh
30
πŸ“ This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Kiwi Power (formerly Taunton Battery Storage) /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.020082+-3.154791
Coordinates
51.020082, -3.154791
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
343 / 7152

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Fideoak Mills / south west
Go live / estimated go live
2020-08-01 /
MW
30
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 21/09/2022

2023-07
Record Last Updated (dd/mm/yyyy): 21/09/2022 ->

2022-10
Record Last Updated (dd/mm/yyyy): 21/02/2020 -> 21/09/2022
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Operational: -> 01/08/2020
status: construction -> operation 🍾 πŸŽ‰ 🍸