Fideoak Mills ππ
Status
operation
Country / State / Closest City
π¬π§ uk / south west /
Dates
First heard |
2020-02-21 |
Construction start |
2019-09-01 |
Operation start |
2020-08-01 |
Estimated start |
|
Construction time |
11 months -> 2 MWh/m
|
Capacity in MWh
30
π This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Kiwi Power (formerly Taunton Battery Storage) /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.020082+-3.154791
Coordinates
51.020082, -3.154791
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
343 / 7152
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Fideoak Mills / south west
Go live / estimated go live
2020-08-01 /
MW
30
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 21/09/2022
2023-07
Record Last Updated (dd/mm/yyyy): 21/09/2022 ->
2022-10
Record Last Updated (dd/mm/yyyy): 21/02/2020 -> 21/09/2022
Development Status: Under Construction -> Operational
Development Status (short): Under Construction -> Operational
Operational: -> 01/08/2020
status: construction -> operation πΎ π πΈ