Perseverance Road ππ
Status
planning
Country / State / Closest City
π¬π§ uk / west midlands /
Dates
First heard |
2020-01-31 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
20
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Noriker Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.068196+-2.719292
Coordinates
52.068196, -2.719292
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
325 / 7061
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Perseverance Road / west midlands
Go live / estimated go live
/
MW
20
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 24/02/2022
2023-07
Record Last Updated (dd/mm/yyyy): 24/02/2022 ->
2022-07
Development Status: Planning Permission Granted -> Revised
Development Status (short): Awaiting Construction -> Revised
Address: Land At Perseverance Road, Perseverance Road, Hereford, Hereford & Worcester -> Land At Perseverance Road, Perseverance Road, Hereford,
2022-04
Record Last Updated (dd/mm/yyyy): 29/11/2021 -> 24/02/2022
2021-12
Record Last Updated (dd/mm/yyyy): 31/01/2020 -> 29/11/2021
CHP Enabled: -> No