Riverside Energy Park ππ
Status
planning
Country / State / Closest City
π¬π§ uk / london /
Dates
First heard |
2020-04-09 |
Construction start |
|
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
20
π This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Cory Riverside Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.504508+0.153302
Coordinates
51.504508, 0.153302
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
315 / 7036
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Riverside Energy Park / london
Go live / estimated go live
/
MW
20
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 06/04/2022
2023-07
Record Last Updated (dd/mm/yyyy): 06/04/2022 ->
2022-10
Planning Permission Expired: -> 09/04/2025
2022-04
Record Last Updated (dd/mm/yyyy): 24/06/2020 -> 06/04/2022