Enderby Storage, Redcomb Farm πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / east midlands /
Dates
First heard 2020-08-21
Construction start 2021-04-01
Operation start
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Statera Energy / Enderby Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.597459+-1.223231
Coordinates
52.597459, -1.223231
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
309 / 7044

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Enderby Storage, Redcomb Farm / east midlands
Go live / estimated go live
/
MW
49
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 01/04/2021

2023-07
Record Last Updated (dd/mm/yyyy): 21/08/2020 ->