Mannington Battery Storage Plant πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2020-05-27
Construction start 2020-11-01
Operation start 2021-10-01
Estimated start
Construction time 11 months -> 4 MWh/m
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Still Waters Green Technology /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.553544+-1.814961
Coordinates
51.553544, -1.814961
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
307 / 7024

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Mannington Battery Storage Plant / south west
Go live / estimated go live
2021-10-01 /
MW
49
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 14/09/2022

2023-07
Record Last Updated (dd/mm/yyyy): 14/09/2022 ->

2022-10
Record Last Updated (dd/mm/yyyy): 27/05/2020 -> 14/09/2022
Operator (or Applicant): Public Power Solutions -> Still Waters Green Technology
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Planning Permission Expired: -> 28/02/2021
Under Construction: -> 01/11/2020
Operational: -> 01/10/2021
status: planning -> operation 🍾 πŸŽ‰ 🍸