Nether Moor Field πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / yorkshire and humber /
Dates
First heard 2020-05-27
Construction start
Operation start 2020-09-01
Estimated start
Construction time
Capacity in MWh
49
πŸ“ This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Thurcroft Energy (Max Design Consultancy) /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.401251+-1.26828
Coordinates
53.401251, -1.26828
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
305 / 7019

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Nether Moor Field / yorkshire and humber
Go live / estimated go live
2020-09-01 /
MW
49
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/05/2020

2023-07
Record Last Updated (dd/mm/yyyy): 27/05/2020 ->

2022-10
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Planning Permission Expired: -> 22/11/2022
Operational: -> 01/09/2020
status: planning -> operation 🍾 πŸŽ‰ 🍸