Drax Re-Power πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / yorkshire and humber /
Dates
First heard 2018-05-24
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Drax Group /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.732262+-0.995254
Coordinates
53.732262, -0.995254
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
303 / 7017

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2021-09 report):

Plant Name / State
Drax Re-Power / yorkshire and humber
Go live / estimated go live
/
MW
200
Status
planning
Changes:
2024-04
Planning Permission Expired: NA ->

2024-01
Record Last Updated (dd/mm/yyyy): -> 02/01/2020

2023-07
Record Last Updated (dd/mm/yyyy): 02/01/2020 ->
Planning Permission Expired: -> NA