Aikengall II Community Wind Farm Battery πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland /
Dates
First heard 2019-07-04
Construction start 2020-12-01
Operation start 2021-06-01
Estimated start
Construction time 6 months -> 13 MWh/m
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Community Wind Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.907534+-2.513953
Coordinates
55.907534, -2.513953
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
294 / 7015

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Aikengall II Community Wind Farm Battery / scotland
Go live / estimated go live
2021-06-01 /
MW
80
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/03/2023

2023-07
Record Last Updated (dd/mm/yyyy): 21/08/2020 ->
Turbine Capacity (MW): 4.2 ->
No. of Turbines: 19 ->
Height of Turbines (m): 145 ->
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Under Construction: -> 01/12/2020
Operational: -> 01/06/2021
status: planning -> operation 🍾 πŸŽ‰ 🍸

2022-04
Turbine Capacity (MW): 4.20 -> 4.2
Height of Turbines (m): 145.00 -> 145