Aikengall II Community Wind Farm Battery ππ
Status
operation
Country / State / Closest City
π¬π§ uk / scotland /
Dates
First heard |
2020-08-21 |
Construction start |
2020-12-01 |
Operation start |
2021-06-01 |
Estimated start |
|
Construction time |
6 months -> 13 MWh/m
|
Capacity in MWh
80
π This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Community Wind Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.907534+-2.513953
Coordinates
55.907534, -2.513953
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
294 / 7015
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Aikengall II Community Wind Farm Battery / scotland
Go live / estimated go live
2021-06-01 /
MW
80
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/03/2023
2023-07
Record Last Updated (dd/mm/yyyy): 21/08/2020 ->
Turbine Capacity (MW): 4.2 ->
No. of Turbines: 19 ->
Height of Turbines (m): 145 ->
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Under Construction: -> 01/12/2020
Operational: -> 01/06/2021
status: planning -> operation πΎ π πΈ
2022-04
Turbine Capacity (MW): 4.20 -> 4.2
Height of Turbines (m): 145.00 -> 145