Ray Battery Storage Facility πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / north east /
Dates
First heard 2017-07-25
Construction start 2022-07-01
Operation start 2022-10-01
Estimated start
Construction time 3 months -> 6 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Vattenfall Wind Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.165618+-2.078
Coordinates
55.165618, -2.078
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
283 / 6943

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2021-09 report):

Plant Name / State
Ray Battery Storage Facility / north east
Go live / estimated go live
2022-10-01 /
MW
20
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/03/2023

2023-07
Record Last Updated (dd/mm/yyyy): 21/09/2020 ->
Development Status: Planning Permission Granted -> Operational
Development Status (short): Awaiting Construction -> Operational
Under Construction: -> 01/07/2022
Operational: -> 01/10/2022
status: planning -> operation 🍾 πŸŽ‰ 🍸

2022-07
Address: Ray Wind Farm, Kirkwhelpington, Newcastle Upon Tyne, Northumberland -> Ray Wind Farm, Kirkwhelpington, Newcastle Upon Tyne,