Chelveston Renewable Energy Park 📊📏
Status
construction
Country / State / Closest City
🇬🇧 uk / east midlands /
Dates
First heard |
2020-05-27 |
Construction start |
2019-07-01 |
Operation start |
|
Estimated start |
|
Construction time |
|
Capacity in MWh
20
📏 This is an estimate
Maximum Power in MW
20
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Federal Estates /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:52.310725+-0.530869
Coordinates
52.310725, -0.530869
✅ The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
273 / 6941
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Chelveston Renewable Energy Park / east midlands
Go live / estimated go live
/
MW
20
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 27/05/2020
2023-07
Record Last Updated (dd/mm/yyyy): 27/05/2020 ->
2022-07
Address: Chelveston Renewable Energy Pa, The Airfield, Chelveston, Wellingborough,�Northamptonshire -> Chelveston Renewable Energy Pa, The Airfield, Chelveston, Wellingborough,�