Status
operation
Country / State / Closest City
π¬π§ uk / eastern /
Dates
First heard |
2019-01-03 |
Construction start |
2017-01-15 |
Operation start |
2017-06-15 |
Estimated start |
|
Construction time |
5 months -> 9 MWh/m
|
Capacity in MWh
49
π This is an estimate
Maximum Power in MW
49
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Statera Energy/ InfraRed Capital /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.937437+0.119184
Coordinates
51.937437, 0.119184
β
The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
Internal / External id
260 / 6898
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report
(Project first appeared in the
2021-09
report):
Plant Name / State
Pelham / eastern
Go live / estimated go live
2017-06-15 /
MW
49
Status
operation
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): -> 03/01/2019
2023-07