Pelham ππ 
Status 
operation 
Country / State / Closest Cityπ¬π§ uk / eastern / 
Dates
    
        
            
                | First heard | 2019-01-03 | 
            
                | Construction start | 2017-01-15 | 
            
                | Operation start | 2017-06-15 | 
            
                | Estimated start |  | 
            
            
                | Construction time | 5 months -> 9 MWh/m | 
        
     
 
Capacity in MWh 
    49
     
π  This is an estimate 
Maximum Power in MW49
Manufacturer 
Type / Number of Packs / Cells /  / 
Customer / Owner / Developer / Statera Energy/ InfraRed Capital /  
Use case
Link to google maps satellite viewhttp://maps.google.com/maps?z=19&t=k&q=loc:51.937437+0.119184 
Coordinates
    51.937437, 0.119184 
    
 β
 The site is known, coords are +/- 1 kilometer
Notes
    
     
     
Project website  
Sources
     
Internal / External id
    260 / 6898
 UK REPD data 
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
    https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 
2024-04 report 
(Project first appeared in the 
2021-09 report):
Plant Name / State
Pelham / eastern
Go live / estimated go live2017-06-15 / 
MW49
Statusoperation
Changes:
    2024-01
    
        Record Last Updated (dd/mm/yyyy):  -> 03/01/2019 
     
    
    
2023-07
    
        Record Last Updated (dd/mm/yyyy): 03/01/2019 ->