Dunkirk 2 πŸ‘€

Status
operation
Country / State / Closest City
πŸ‡«πŸ‡· france / / Dunkirk
Dates
First heard
Construction start
Operation start 2021-12-22
Estimated start
Construction time
Capacity in MWh
31
Maximum Power in MW
31
Manufacturer
Saft
Type / Number of Packs / Cells
Intensium Max 20 High Energy (20ft container) / 16 / NMC
Customer / Owner / Developer
/ Total /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:51.030471+2.255373
Coordinates
51.030471, 2.255373
βœ… The site is known, coords are +/- 1 kilometer
Notes
saft is owned by total
Project website
Sources
https://www.energy-storage.news/frances-largest-battery-storage-facility-expanded-to-61mw-61mwh-as-second-phase-completed/
Internal / External id
258 /