Victorian Big Battery πŸ‘€

Status
operation
Country / State / Closest City
πŸ‡¦πŸ‡Ί australia / victoria / geelong
Dates
First heard 2020-11-01
Construction start 2021-01-01
Operation start 2021-12-08
Estimated start
Construction time 11 months -> 40 MWh/m
Capacity in MWh
450
Maximum Power in MW
300
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 212 /
Customer / Owner / Developer
Neoen Australia / /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:-38.037741+144.290949
Coordinates
-38.037741, 144.290949
βœ… Coords are exact (+/- 50m)
Notes
incident: fire of 2 megapacks on 30.7.2021, burned for ca 3 days, the site was not live yet, it happened during a internal test
2021-09-03 moving project back to construction
Project website
https://victorianbigbattery.com.au/
Sources
https://www.teslarati.com/telsa-megpack-victorian-big-battery-launched/
https://techau.com.au/victorias-grid-just-got-greener-thanks-to-212-tesla-megapack-batteries-300mw-450mwh/
https://www.bestmag.co.uk/indnews/tesla%E2%80%99s-lithium-ion-megapack-causes-three-day-fire-during-test-australian-300mw-ess
https://www.energy-storage.news/victorian-big-battery-australias-biggest-battery-storage-system-at-450mwh-is-online/
Internal / External id
2 /