Muchea Battery πŸ‘€

Status
construction
Country / State / Closest City
πŸ‡¦πŸ‡Ί australia / western australia /
Dates
First heard
Construction start 2025-10-01
Operation start
Estimated start 2027-10
Construction time
Capacity in MWh
905
Maximum Power in MW
164
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 252 /
Customer / Owner / Developer
/ Neoen /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:-31.556054+115.958459
Coordinates
-31.556054, 115.958459
βœ… The site is known, coords are +/- 1 kilometer
Notes
got the start estimate from the gov website
Project website
https://mucheabattery.com.au/
Sources
https://neoen.com/en/news/2025/neoen-launches-first-6-hour-battery-in-muchea-delivers-collie-battery-2-both-in-western-australia/
https://esdnews.com.au/construction-begins-on-muchea-battery-in-wa/
https://minister.dcceew.gov.au/bowen/media-releases/more-mega-batteries-wa-power-homes-day-and-night?utm_source=chatgpt.com
Internal / External id
1811 /