Iron Springs BESS πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / utah /
Dates
First heard 2025-08
Construction start
Operation start
Estimated start 2026-02
Construction time
Capacity in MWh
160
πŸ“ This is an estimate
Maximum Power in MW
80
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Iron Springs BESS, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.696903+-109.717891
Coordinates
40.696903, -109.717891
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1810 / 69041

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-09 report (Project first appeared in the 2025-08 report):

Plant Name / State
Iron Springs BESS / UT
go live / power
2026-02 / 80MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
69041 / ISBA
Entity name / entity id
Iron Springs BESS, LLC / 67231