Stoneridge Solar, LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2025-08 |
Construction start |
|
Operation start |
|
Estimated start |
2025-08 |
Construction time |
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ RWE Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.51523936488624+-95.46174719022643
Coordinates
33.51523936488624, -95.46174719022643
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1809 / 69027
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-09
report (Project first appeared in the
2025-08
report):
Plant Name / State
Stoneridge Solar, LLC / TX
go live / power
2025-08 / 100MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
69027 / SSBA
Entity name / entity id
RWE Clean Energy / 67192
Changes: