Glenarm BESS Plant πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2025-09
Construction start
Operation start
Estimated start 2026-08
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Glenarm BESS LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.129475373876254+-121.2791257566415
Coordinates
41.129475373876254, -121.2791257566415
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1801 / 69024

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-09 report (Project first appeared in the 2025-09 report):

Plant Name / State
Glenarm BESS Plant / CA
go live / power
2026-08 / 25MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
69024 / GLNB1
Entity name / entity id
Glenarm BESS LLC / 67223