Roadrunner Reserve Phase 2 πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2025-09
Construction start
Operation start
Estimated start 2026-04
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Tucson Electric Power Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.269177450183875+-109.59724395000252
Coordinates
36.269177450183875, -109.59724395000252
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1798 / 68937

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-09 report (Project first appeared in the 2025-09 report):

Plant Name / State
Roadrunner Reserve Phase 2 / AZ
go live / power
2026-04 / 200MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
68937 / RDR2
Entity name / entity id
Tucson Electric Power Co / 24211
Changes: