CO Bar C Solar and BESS πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2025-08 |
Construction start |
|
Operation start |
|
Estimated start |
2027-06 |
Construction time |
|
Capacity in MWh
412
π This is an estimate
Maximum Power in MW
206
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Clenera DevCo LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.20821732387876+-109.68893372573432
Coordinates
36.20821732387876, -109.68893372573432
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1797 / 69058
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-09
report (Project first appeared in the
2025-08
report):
Plant Name / State
CO Bar C Solar and BESS / AZ
go live / power
2027-06 / 206MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
69058 / CBCBA
Entity name / entity id
Clenera DevCo LLC / 66571
Changes: