Holes Bay
π
π€
Status
operation
Country / State / Closest City
π¬π§ uk / south west / Poole
Dates
First heard
2020-04-29
Construction start
2020-01-01
Operation start
2020-09-18
Estimated start
Construction time
8 months -> 1 MWh/m
Capacity in MWh
15
Maximum Power in MW
15
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 6 /
Customer / Owner / Developer
Harmony Energy Ltd / Fotowatio Renewable Ventures BV / Harmony Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:50.726324+-1.990215
Coordinates
50.726324, -1.990215
β The site is known, coords are +/- 1 kilometer
Notes
Project website
Sources
https://www.teslarati.com/tesla-megapack-autobidder-uk-energy-grid-debut/
https://www.bloomberg.com/news/articles/2020-09-18/six-giant-tesla-batteries-used-to-keep-lights-on-in-britain
https://www.harmonyenergy.co.uk/general/video-holes-bay-battery-energy-storage-plant/
https://frv.com/en/projects/holes-bay/
Internal / External id
17 / 7688
UK REPD data
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the
2024-04
report (Project first appeared in the
2021-09
report):
Plant Name / State
Holes Bay / south west
Go live / estimated go live
/
MW
15
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 29/04/2020 -> 14/01/2020