Western Downs Battery (phase 2) πŸ‘€

Status
planning
Country / State / Closest City
πŸ‡¦πŸ‡Ί australia / queensland / South West Queensland
Dates
First heard 2024-08-27
Construction start
Operation start
Estimated start 2026
Construction time
Capacity in MWh
540
Maximum Power in MW
270
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / /
Customer / Owner / Developer
AGL Energy Limited / Neoen /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:-26.976+150.666
Coordinates
-26.976, 150.666
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
https://westerndownsgreenpowerhub.com.au/
Sources
https://reneweconomy.com.au/queenslands-biggest-battery-to-double-in-size-after-agl-signs-virtual-contract
https://neoen.com/en/news/2024/neoen-to-build-stage-2-of-western-downs-battery-after-signing-a-200-mw-virtual-battery-contract-with-agl-energy/
Internal / External id
1509 /