Lumina II Solar Project πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2024-07
Construction start
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
320
πŸ“ This is an estimate
Maximum Power in MW
160
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ IP Lumina II, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.454054+-95.273438
Coordinates
33.454054, -95.273438
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1500 / 65644

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2024-07 report):

Plant Name / State
Lumina II Solar Project / TX
go live / power
2024-12 / 160MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65644 / LU2BA
Entity name / entity id
IP Lumina II, LLC / 64927
Changes: