Moat Lane, Wickersley - Battery Storage Facility πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / yorkshire and humber /
Dates
First heard 2024-03-18
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Harmony Energy Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:53.406502+-1.268596
Coordinates
53.406502, -1.268596
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1462 / 16065

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2024-04 report):

Plant Name / State
Moat Lane, Wickersley - Battery Storage Facility / yorkshire and humber
Go live / estimated go live
/
MW
100
Status
planning
Changes: