Jamesfield Organic Centre - Battery Storage πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / scotland / Abernethy
Dates
First heard 2022-09-28
Construction start 2023-01-01
Operation start 2024-03-19
Estimated start
Construction time 14 months -> 7 MWh/m
Capacity in MWh
98
Maximum Power in MW
49
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 26 / LFP
Customer / Owner / Developer
Tag Energy / Harmony Energy Storage /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:56.347678+-3.298351
Coordinates
56.347678, -3.298351
βœ… The site is known, coords are +/- 1 kilometer
Notes
extrapolated the cost from the 60 million investment for 60% and then split it across both projects mentioned in article
Project website
Sources
https://reneweconomy.com.au/tag-energy-to-use-tesla-megapacks-in-two-new-battery-storage-projects-in-uk/
https://www.harmonyenergyplanning.co.uk/jamesfield/
Internal / External id
130 / 10863

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2022-07 report):

Plant Name / State
Jamesfield Organic Centre - Battery Storage / scotland
Go live / estimated go live
/
MW
49
Status
construction
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 12/01/2023 -> 24/03/2022
Planning Authority: Perth and Kinross Council -> Perth & Kinross Council

2023-07
Planning Permission Expired: 28/09/2025 ->

2023-01
Record Last Updated (dd/mm/yyyy): 07/06/2022 -> 12/01/2023
Development Status: Planning Application Submitted -> Under Construction
Development Status (short): Application Submitted -> Under Construction
Planning Permission Granted: -> 28/09/2022
Planning Permission Expired: -> 28/09/2025
Under Construction: -> 01/01/2023
status: planning -> construction πŸ—οΈ