Battery Energy Storage Facility in Londonderry πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / northern ireland /
Dates
First heard 2023-11-22
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
34
πŸ“ This is an estimate
Maximum Power in MW
34
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Heron Storage Ltd /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:55.034435+-7.208204
Coordinates
55.034435, -7.208204
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1283 / 15303

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2024-01 report):

Plant Name / State
Battery Energy Storage Facility in Londonderry / northern ireland
Go live / estimated go live
/
MW
34
Status
planning
Changes: