Wareham Road, Scouse Farm - Battery Storage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / south west /
Dates
First heard 2023-11-03
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Ylem Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:50.786682+-2.931865
Coordinates
50.786682, -2.931865
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1275 / 15165

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2024-01 report):

Plant Name / State
Wareham Road, Scouse Farm - Battery Storage / south west
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2024-04
Record Last Updated (dd/mm/yyyy): 03/11/2023 -> 07/03/2024
Development Status: Planning Application Submitted -> Revised
Development Status (short): Application Submitted -> Revised
Are they re-applying (New REPD Ref): -> 15962
Planning Application Withdrawn: -> 26/01/2024