Flatterton Farm, Flatterton Road - Battery Storage ππ 
Status 
planning 
Country / State / Closest Cityπ¬π§ uk / scotland / 
Dates
    
        
            
                | First heard | 2023-11-02 | 
            
                | Construction start |  | 
            
                | Operation start |  | 
            
                | Estimated start |  | 
            
            
                | Construction time |  | 
        
     
 
Capacity in MWh 
    49
     
π  This is an estimate 
Maximum Power in MW49
Manufacturer 
Type / Number of Packs / Cells /  / 
Customer / Owner / Developer / Big Battery (Flatterton Farm) Limited /  
Use case
Link to google maps satellite viewhttp://maps.google.com/maps?z=19&t=k&q=loc:55.9331+-4.846146 
Coordinates
    55.9331, -4.846146 
    
 β
 The site is known, coords are +/- 1 kilometer
Notes
    
     
     
Project website  
Sources
     
Internal / External id
    1273 / 15154
 UK REPD data 
The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
    https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 
2024-04 report 
(Project first appeared in the 
2024-01 report):
Plant Name / State
Flatterton Farm, Flatterton Road - Battery Storage / scotland
Go live / estimated go live / 
MW49
Statusplanning
Changes: