Whelley Hill Farm, Worset Lane - Battery Energy Storage πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / north east /
Dates
First heard 2023-12-07
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Reliance Energy Limited /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.69977+-1.301359
Coordinates
54.69977, -1.301359
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1130 / 13246

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-01 report (Project first appeared in the 2023-07 report):

Plant Name / State
Whelley Hill Farm, Worset Lane - Battery Energy Storage / north east
Go live / estimated go live
/
MW
50
Status
planning
Changes:
2024-01
Record Last Updated (dd/mm/yyyy): 20/02/2023 -> 02/01/2024
Development Status: Planning Application Submitted -> Planning Permission Granted
Development Status (short): Application Submitted -> Awaiting Construction
Planning Authority: Hartlepool Council -> Hartlepool Borough Council
Planning Permission Expired: -> 07/12/2026