Highfield Energy Park πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡¬πŸ‡§ uk / north east /
Dates
First heard 2023-06-09
Construction start
Operation start
Estimated start
Construction time
Capacity in MWh
12
πŸ“ This is an estimate
Maximum Power in MW
12
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Exagen /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:54.897962+-1.902172
Coordinates
54.897962, -1.902172
βœ… The site is known, coords are +/- 1 kilometer
Notes

Project website
Sources
Internal / External id
1107 / 12312

UK REPD data

The government data source for this battery is the UK Renewable Energy Planning Database (REPD)
https://www.gov.uk/government/publications/renewable-energy-planning-database-monthly-extract
Info from the 2024-04 report (Project first appeared in the 2023-07 report):

Plant Name / State
Highfield Energy Park / north east
Go live / estimated go live
/
MW
12
Status
planning
Changes: